Truck drivers using the Newell Highway between West Wyalong and Forbes can have their say on a plan to move and seal an existing informal truck stopping area at Marsden. It’s part of a $140.8 million flood-mitigation project now at concept-design stage, according to the joint government announcement.
The proposal covers 6.2 kilometres across four sections. It would raise parts of the road, improve drainage and strengthen pavement. The aim is to shorten closures, not guarantee the highway stays open in a flood. At Marsden, flooding closed the road for seven weeks in 2022 and six weeks in 2016.
The environmental review proposes a 100-metre northbound stopping area marked with green reflectors, about 160 metres south of the existing spot. The shift would make room for a culvert extension.
The environmental review also proposes oversize-vehicle holding bays at each end of the works during construction. Reusing those bays later is an option, not a commitment to extra permanent truck parking.

Have your say
If you run this route, tell Transport for NSW what combinations the relocated stopping area needs to fit, how much room drivers need to get in and out, and where trucks can safely stop during construction. Use the consultation page to make a formal submission or mark an issue on the project map.
Feedback closes Friday 18 December 2026. You can also email your submission to newell.upgrade@transport.nsw.gov.au. Include an email or postal address if you want a formal response in the submissions report.
Correction, 28 November 2026: An earlier version advised readers to submit by 15 December because official sources listed different dates. Transport for NSW has confirmed 18 December and says the earlier date was incorrect.