Kuranda bridge replacement moves to design, but the 42.5-tonne limit stays

The contract to replace the Barron River bridge at Kuranda has been awarded, but the existing crossing on the Kennedy Highway remains subject to a 42.5-tonne load limit. The Queensland Government announced on 20 November that a joint venture of Seymour Whyte, VSL and Arup would design and build the replacement. The next 12 months…

The contract to replace the Barron River bridge at Kuranda has been awarded, but the existing crossing on the Kennedy Highway remains subject to a 42.5-tonne load limit.

The Queensland Government announced on 20 November that a joint venture of Seymour Whyte, VSL and Arup would design and build the replacement. The next 12 months are for detailed design, site investigations, environmental assessments and further community consultation. Construction has not started.

Transport and Main Roads expects construction to start in 2028 and the new bridge to open in 2031. The federal and Queensland governments have committed $245 million each. The $490 million is the total project investment, not a stated value for the joint venture’s contract.

KBR said on 24 November it had been selected to independently verify the design. The new bridge will sit downstream of the existing crossing and have wider lanes, upgraded approaches and a separate shared path.

In its April 2025 business case, TMR compared 48 minutes on the direct Mareeba–Cairns route with two hours and 50 minutes via the Palmerston Highway. Those are planning estimates, not live travel times or confirmation that a specific combination can use the alternate route.

Separate cyclone reconstruction works close Kuranda Range Road from 9 pm to 4 am on Sunday to Thursday nights through 10 December, conditions permitting. TMR schedules one midnight release in each direction. The bridge load limit still applies. Check the live heavy-vehicle report before travelling.

See WWTG’s current Queensland freight restrictions for other access changes.